RELIANCE GREEN ENERGY PTE LTD
Sengkang General Hospital · Preliminary proposal
Illustrative hospital rooftop with LIAM F1 spiral wind turbines and cooling towers

Hospital facilities & sustainability

SENGKANG GENERAL HOSPITAL

Cooling tower airflow.
Lower operating costs.

Put wasted cooling tower airflow to work with LIAM F1 R-1600 wind turbines, converting it into electricity to reduce hospital energy costs.

A measured pilot to assess rooftop airflow recovery, protect cooling performance and establish a credible investment case.

Prepared by Reliance Green Energy Pte Ltd

Illustrative proposal · Rooftop concept visual01 / 09

An operating-cost opportunity with a measured approval path

The proposal targets electricity cost reduction and progress toward hospital carbon neutrality goals through recovery of existing mechanical airflow.

01 · Rooftop operations

Zero interference as a design objective

Use suitable space beside existing cooling towers. Preserve service routes, lifting zones, emergency access and any protected aviation clearances.

02 · Financial case

SGD 755,040 annual savings scenario

Validate savings against the hospital’s avoided electricity price, net generation and operating costs. Measured output can reduce exposure to electricity price changes.

03 · Investment discipline

Five-year payback target

Apply a proposed SGD 3.5 million capital cap. Full rollout proceeds only when the pilot supports the required net savings and technical acceptance criteria.

Sengkang Hospital rooftop cooling tower overview without wind turbines
Savings, cap and payback target supplied in the brief. 02 / 09

Site opportunity

A consistent array beside the cooling towers

7 × 13 × 2 = 182

Proposed planning layout: seven rows of thirteen cooling tower outlets, with two turbines per cooling tower, giving 26 turbines per row.

  • Confirm the actual fan count, outlet geometry and duty cycles during the survey.
  • Locate independent supports beside the towers, with rotor alignment based on measured airflow.
  • Maintain separation for safe access and future fan or motor replacement.
182 turbines at 5 kW nameplate each = 910 kW total peak capacity. Nameplate capacity does not establish continuous output.
Verified 7-row × 13-tower layoutReserved for a correctly counted rooftop image.
Two matching turbines beside each tower.
03 / 09

3D operating principle

How cooling tower airflow produces electricity

Cooling tower deflector routes airflow to LIAM F1 rotor, controller, inverter and approved loads, with optional battery

Airflow recovery

An engineered guide directs a portion of the tower’s discharge toward the rotor while preserving outlet clearance.

Rotation & generation

Airflow applies torque to the spiral blades. The horizontal shaft drives the generator.

Usable electricity

The controller and inverter condition the output for an approved connection to the building’s electrical system.

Conceptual arrangement. Net energy benefit includes any change in fan demand and system losses.

Cooling-tower airflow recovery principle04 / 09

Technical validation

Net energy recovery with protected cooling performance

Cooling tower discharge provides the airflow source. The pilot must demonstrate the electrical benefit after any additional fan demand and system losses.

  • Log airflow across fan speeds and representative plant loads.
  • Measure turbine output alongside fan electricity, static pressure and cooling performance.
  • Confirm structural loads, vibration, noise and maintenance clearances.
  • Review electrical protection and integration with the hospital’s facilities team.
Net recovered energy = usable turbine generation − incremental fan energy − auxiliary consumption.
Operating concept videoReserved for rotor animation with the poles, towers and camera kept stationary

A visual simulation illustrates the concept. It does not verify generation or establish that cooling performance remains unchanged.

05 / 09

Solar & wind comparison

10 × 570 W solar panels vs. one LIAM F1 R-1600

Daily electricity output and savings using the supplied operating assumptions and SGD 0.22/kWh.

No.Parameter10 × 570 W solar panelsOne LIAM F1 R-1600 turbine
1Rated maximum power5,700 W5,050 W (supplied figure)
2Assumed operating output1,425 W (25% of rated power)2,500 W (50% of nominal 5 kW)
3Assumed daily operating hours4.5 peak sun hours24 airflow hours
4Equipment costSGD 150 × 10 = SGD 1,500SGD 5,500
5Daily / annual electricity output6.4125 kWh/day
2,308.5 kWh/year
60 kWh/day
21,600 kWh/year
6Daily savings at SGD 0.22/kWhSGD 1.41SGD 13.20
7Monthly savingsSGD 42.32SGD 396.00
8Annual savingsSGD 507.87SGD 4,752.00
9Equipment cost recovered in year 133.86%86.40%
10Equipment cost remaining after year 1SGD 992.13SGD 748.00
11Estimated avoided CO₂ per year0.96 tonnes8.99 tonnes

Note: solar-panel evaluation in Singapore

  • Peak sun hours: approximately 4.0–4.5 hours/day annual average.
  • Equivalent annual peak sun hours: approximately 1,460–1,640 hours/year.
  • Practical PV yield: around 1,200–1,400 kWh per installed kWp per year, depending on roof orientation, shading, temperature, inverter losses, soiling and system availability.
06 / 09

Industrial feasibility calculator

Check Your Facility

Enter the number of cooling tower fans. This presentation sizes two turbines per fan and applies the R-1600 website’s annual yield preset to each turbine.

Per-turbine reference presets reproduced from the Reliance R-1600 calculator, checked 9 October 2026. Default: 91 fans × 2 turbines = 182 turbines.

This presentation uses two turbines per fan. The source website sizes one turbine per fan. Both use fixed annual-yield presets and 0.416 kg CO₂/kWh. Outlet dimensions and access do not change its numerical results. Its feasibility score is a preset, not an engineering certification. Estimates require site validation and do not account for incremental fan demand or losses.

Preliminary feasibility rating

Recommended array sizing

Estimated annual output

Carbon offset estimate

Tonnes CO₂ avoided / year, source-model basis

Screening estimate. Generation and financial projections use different assumptions.07 / 09

Turnkey scope & risk mitigation

A defined scope with hospital acceptance gates

ScopeProposal inclusion
HardwareTurbines, controllers, inverters and monitoring
Installation materialsSupports, anchors, isolation, cabling and airflow guides where required
Installation & commissioningDelivery, lifting, installation, protection tests and handover
Endorsement feesPE and LEW services and applicable approval fees, itemised in the quotation
Safety complianceWork permits, lifting plans, fall protection and hospital contractor requirements

Final quotation must identify inclusions, exclusions, recurring costs and maintenance responsibility within the proposed capital cap.

Risk controls

  • Cooling performance: compare pre- and post-installation plant measurements.
  • Operational continuity: agree phased work windows and preserve hospital access.
  • Structural safety: obtain design review before installation.
  • Electrical integration: test protection and isolation before energising.
  • Investment risk: apply measured net-output and savings thresholds before rollout.

Installation at Infineon Technologies, Singapore

08 / 09

Site survey & pilot approval

The next decision is a measured pilot

Approve access for a site survey and preparation of a costed pilot proposal. Full-array investment follows technical and financial acceptance.

01

Site survey

Confirm outlet inventory, operating schedules, airflow, support locations and access constraints.

02

Pilot proposal

Agree turbine positions, installation scope, programme, measurement plan and acceptance thresholds.

03

Pilot approval

Review itemised cost, professional endorsements and hospital safety requirements before installation.

04

Rollout decision

Use measured net energy and operating costs to test the five-year payback target and SGD 3.5 million cap.

Pilot location or closing videoReserved for the selected pilot tower and final project visual
Survey and proposal approval do not constitute approval of full-array capital expenditure.09 / 09